Middleton Grange

MIDDLETON GRANGE TOWN CENTRE
60 – 80 Southern Cross Ave

CLIENT: Manta Group Pty Limited
ARCHITECT: Design Competiton Pending
ENGINEER: Xavier Knight Consulting Engineers (Structural); Wyndham Prince (Civil & Services)
BANK FUNDER: TBC
COUNCIL: Liverpool City Council

VITAL
STATISTICS

  • PROJECT ADDRESS: 60 – 80 Southern Cross Ave and 45 – 65 Hall Circuit, Middleton Grange
  • PROJECT NAME: Middleton Grange Town Centre
  • STATUS: Design and Pre-construction
  • COMMENCED: 2017 (Planning)
  • COMPLETION: 2024; With multiple lot and staged delivery, lots will be completed in succession from construction commencement in 2021 – timing deliverables are set conveniently with the delivery of the new Badgery’s Creek Airport.

CONTRACT
TYPE AND
SCOPE

  • Design & Construct
  • DA coordination
  • Re-zoning with State Planning and Council
  • Re-zoning approval
  • Civil subdivision
  • Roadworks/Civil